Table 2 Cost comparison of conventional and bioengineering mitigation works (Rai 2010)

From: Landslide hazard map: tool for optimization of low-cost mitigation

Item

Unit

Quantity

Cost (NRs.)

Cost of Bioengineering works

  

5,875,704.00

 Slide clearance

m3

390

26,910.00

 Construction of plum concrete wall

m3

1350

4,872,150.00

 Construction of gabion wall

m3

120

157,920.00

 Construction of dry wall

m3

107

95,444.00

 Rill and ridge formation

m2

85

15,045.00

 Slope trimming

m2

1807

38,140.00

 Backfilling

m3

896

103,040.00

 Installation of sub-soil drain

m

180

177,480.00

 Coir netting

m2

877

156,106.00

 Grass plantation

m2

1893

132,510.00

 Brushlayering

m

581

18,011.00

 Grass seeds broadcasting on slope

m2

3380

64,220.00

 Shrub seeds sowing on slope

m2

948

10,428.00

 Fruit plantation

no

150

600.00

 Bamboo plantation

no

50

7700.00

Cost of Civil Engineering Works

  

12,201,833.00

 Earth work in excavation

m3

2581

296,815.00

 Earth work in backfilling

m3

7350

845,250.00

 Plum Concrete revetment wall (1:2:4)

m3

1350

4,832,100.00

 Gabion wall

m3

2123

2,793,868.00

 PCC (1:2:4)

m3

280

1,079,400.00

 Cement masonry cut drain in (1:4)

Rm.

200

727,000.00

 Cement masonry surface drain (1:4)

Rm.

120

469,800.00

 Cement masonry chute (1:4)

Rm.

100

643,100.00

 Grass Plantation

m3

7350

514,500.00

  1. (1USD = NRS 98.17 on 09 Oct 2010, Source: Nepal Rastra Bank)